RANELAGH RESIDENCE – Week 2

Week 2 on site has gone as well as week 1, with the vast majority of all the internal excavation and demolition works being completed. Structural steel beams, angles and new oak lintel have been installed so we can take comfort that the house is secure! All internal partitions in the basement have been removed, the new level has been attained and some additional underpinning has been carried out on one of the internal boundary walls. Upstairs has seen the levelling of the floor in the double bedroom and walk in wardrobe and the demolition of both bathrooms.

New raised and levelled floor level in the first floor double bedroom and walk in wardrobe
Original partition wall between en suite and main first floor bathroom
En suite bathroom stripped out leaving us room to design a new walk in double shower.
New level into the double bedroom
A scary look into the excated basement. New steel beam and column have been installed to support the house.
Underpinning of the fireplace in the basement kitchen was needed.
Scenic view from the back!